Complex Sea Breeze: photo essay from the construction site
(08.08.2013)
Construction Week 7: of the building foundation stab, second floor slab and roof slab, walling. Working for the electricians, dredging for the warehouse for villas 1a, 4a and 5.
...
|
Opened the first infrastructure in the complex Dukley Gardens
(08.08.2013)
The complex is open beach that offers sun umbrellas and sun beds, shower stand, a rescue station, cabanas. Pontoons are fitted with a ladder for easy descent into the water and parking waterway.
The complex has a new beach bar, outdoor swimming pool, a café, a restaurant, a stage ...
|
Lustica Bay - construction works progress report
(17.07.2013)
Lustica Bay construction works progress report - photos as per 16.07.2013:
...
|